Building permits in Geneva: APA or DD?
In Geneva, almost all visible works — building, extending, altering, demolishing — require a building permit (autorisation de construire) from the Office des autorisations de construire. There are two main procedures: the fast-track procedure (APA) and the full application (DD).
Two main procedures
| Criterion | APA — fast-track procedure | DD — full application |
|---|---|---|
| Applicable works | Interior alterations, works that do not change the general appearance of the building, small structures, villas in zone 5 without exemptions | All other projects: new buildings, major extensions, projects requiring an exemption |
| Processing time | 30 days | 60 days |
| Consultation of departments | Opinions issued in about 15 days | Opinions issued in about 30 days |
| Publication | The decision is published in the Feuille d'avis officielle (FAO) | Submission and decision published in the Feuille d'avis officielle (FAO) |
Time limits run from the submission of a complete application. If the office requests additional documents, the ordinary procedure’s time limit is suspended until they are received. In practice, a DD often takes more than 60 days: it is best to build this into the schedule from the sketch stage.
Other useful applications
- DP — preliminary application (demande préalable): before drawing detailed plans, obtain a response from the authorities on siting, use, building envelope, volume and access. Useful on a tricky plot or for an ambitious project.
- DR — request for information (demande de renseignement): a non-binding opinion on a specific question.
- M / MPA — demolition: a complete demolition requires a separate application; a partial or interior demolition can be included in the reconstruction project.
- Supplementary application (demande complémentaire): to modify a project already authorised, as long as the occupancy permit has not been issued.
Works often exempt
Some works do not require a permit, provided they do not affect a protected building: interior renovation of a villa without any change in habitable floor area, very small demountable structures, solar panels well integrated into the roof. In a residential building subject to the LDTR, however, even interior works may require a permit. If in doubt, a check before work begins avoids a stop-work order.
How an application proceeds
- Plot analysis: zone, ratios, distances to boundaries, trees, easements, heritage.
- Sketch design and possible preliminary application to validate the volume.
- Compiling the application: single form, thematic forms (energy, trees, safety, etc.) and drawings.
- Online submission on the State of Geneva’s AC-Démat platform (paper submission remains possible).
- Review: departmental opinions, responses to requests for additional information.
- Decision and publication in the FAO, followed by the third-party appeal period before work can begin.
- Start of works, supervision, then certificate of compliance on completion.
The architect’s role
A complete and consistent application from the outset is the best way to keep to the time limits. The architect checks regulatory feasibility, draws the plans, completes the forms, submits the application, responds to the office’s requests and adapts the project if necessary, then supervises the works through to compliance.
Frequently asked questions
Is a permit required for a conservatory or carport in Geneva?
Generally yes, as these structures alter the external appearance and the footprint. Depending on their size and siting, a fast-track procedure (APA) may suffice.
How long should I allow?
30 days under the fast-track procedure and 60 days under the ordinary procedure from a complete application, plus the preparation of the application, any additional information and the third-party appeal period.
Can I submit the application myself?
Applications are submitted online on AC-Démat or on paper to the Office des autorisations de construire. The drawings and technical forms still need careful preparation.
General information, updated October 2026. Every project is different: the rules for a given plot have to be checked case by case.