Building permits in the Pays de Gex
In the Pays de Gex — Ferney-Voltaire, Gex, Divonne, Saint-Genis-Pouilly, Prévessin-Moëns… — works are governed by the French Planning Code (Code de l'urbanisme) and the Pays de Gex intermunicipal local plan (PLUiH). There are two main authorisations: the prior declaration (déclaration préalable) and the building permit (permis de construire).
Prior declaration or building permit?
| Area created (floor area or footprint) | In an urban zone (U) of the PLUiH | Outside urban zones |
|---|---|---|
| Less than 5 m² | No formalities, but the PLUiH must be complied with | No formalities, but the PLUiH must be complied with |
| 5 to 20 m² | Prior declaration | Prior declaration |
| 20 to 40 m² | Prior declaration (extension of an existing building) | Building permit |
| More than 40 m² | Building permit | Building permit |
The greater of the two values applies: floor area or footprint. A new building, such as a detached house, requires a building permit. Façade alterations, changes to windows and doors or to the roof generally require a prior declaration.
The 150 m² threshold
Private individuals may submit their own application as long as the total area of the project — existing plus extension — does not exceed 150 m² of floor area (surface de plancher). Above that, using an architect is mandatory, for a prior declaration as well as for a permit (art. R431-2 of the Code de l'urbanisme).
Processing times
| Application | Standard time limit | Extended time limit (common cases) |
|---|---|---|
| Prior declaration | 1 month | 2 months within the perimeter of a historic monument (opinion of the Architecte des Bâtiments de France) |
| Building permit — detached house | 2 months | 3 months in a protected area |
| Other building permits | 3 months | Depending on the consultations |
The time limit runs from a complete application; if the town hall requests documents, it only starts once they are received. In the Pays de Gex, several historic centres and areas around monuments — in Ferney-Voltaire around Voltaire’s château, for example — require the opinion of the Architecte des Bâtiments de France and lengthen the time limits.
After approval
- Posting of the permit on the site, visible from the public road, throughout the works.
- Third-party appeals: 2 months from proper posting. It is best to wait until this period has expired before starting major works.
- Validity: 3 years to start the works, extendable twice by one year on request.
- Start of works declared at the town hall, then a declaration of completion and compliance at the end of the works.
The Pays de Gex PLUiH
The intermunicipal local plan, which also serves as the local housing programme, sets out, municipality by municipality, the zones, heights, setbacks, footprints, green spaces to be preserved and parking. It is regularly amended: the version in force should be checked with the town hall or Pays de Gex Agglo before designing the project.
The architect’s role
The architect checks the PLUiH rules applicable to the plot, designs the project, prepares the application documents (plans, sections, elevations, landscape integration, explanatory statement), submits the application — online or at the town hall — responds to requests for documents, then supervises the works. For cross-border projects, the architect also bridges the building practices on both sides of the border.
Frequently asked questions
Do I need an architect for a 30 m² extension?
Not necessarily: only if the total floor area of the house after the works exceeds 150 m².
Can a permit be submitted online?
Yes, municipalities must accept planning applications submitted electronically; submission at the town hall remains possible.
What happens if the town hall does not respond?
When the processing period expires, silence in principle constitutes tacit approval, with some exceptions (particularly in protected areas).
General information, updated October 2026. Every project is different: the rules for a given plot have to be checked case by case.