Home / Guides / Building permits in the canton of Vaud

Building permits in the canton of Vaud

In the canton of Vaud — Nyon, Gland, Coppet, Rolle, Morges, Lausanne… — the building permit (permis de construire) is issued by the municipal authority (municipalité) after consultation of the cantonal departments. The procedure is governed by the Planning and Building Act (LATC) and its implementing regulations (RLATC).

Which procedure for which works?

ProcedureApplicable projectsSpecific features
Permit with public consultationNew buildings, extensions, major alterations: the vast majority of projects30-day public consultation (enquête publique), consultation of cantonal departments, decision by the municipal authority
Exemption from consultationMinor works: uncovered swimming pool, garden shed, double garage, certain renovationsThe municipal authority may waive the public consultation; a permit is still required
Supplementary consultationModification of a project already authorisedCovers only the modified elements
Prior siting approval (autorisation préalable d'implantation)Major projects whose principle (siting, volumes) needs validating firstDoes not constitute a building permit; lapses if the permit is not applied for in time

An exemption from consultation is not an exemption from a permit: the municipal authority decides, case by case, whether a project qualifies (art. 111 LATC and art. 72d RLATC). If in doubt, check with the municipality before submitting.

Steps in the procedure

  1. Submission of the application to the municipality, using the cantonal electronic form (State of Vaud online services platform). The application includes plans, sections, elevations, a site plan drawn up by a surveyor and technical documents.
  2. Review by the municipality, which checks compliance with the municipal land-use plan and decides whether the project is subject to public consultation or can be exempted.
  3. Public consultation (enquête publique) for 30 days, starting the day after publication in the Feuille des avis officiels (FAO). The notice also appears in a local newspaper, on the municipal noticeboard (pilier public) and on vd.ch, and profile poles (gabarits) may be required on the site.
  4. Objections and comments: while the consultation is open, anyone can inspect the file at the municipal registry (greffe municipal) and lodge a written objection free of charge.
  5. Consultation of cantonal departments: the Centrale des autorisations en matière de construction (CAMAC) collects the special permits and draws up a summary.
  6. Decision by the municipal authority, which grants or refuses the permit and rules on any objections.

Appeals and starting work

The decision can be appealed to the Administrative and Public Law Court of the Cantonal Court (CDAP) within 30 days. Work can only begin once the permit is final, meaning no appeal has been lodged or any appeal has been dismissed.

After the permit

  • Notice of the start of works to the municipality and, for buildings, to the ECA (Établissement cantonal d'assurance).
  • Setting-out check by a licensed surveyor (ingénieur géomètre breveté) before the walls go up.
  • Occupancy or use permit (permis d'habiter ou d'utiliser), issued by the municipal authority when the works are finished. The premises cannot be occupied without it.

The architect’s role

The architect checks the land-use plan and the municipal regulations that apply to the plot, designs the project, prepares and submits the application documents, answers questions from the municipality and the cantonal departments during the review, then oversees the works up to the occupancy permit.

Frequently asked questions

Do I need a permit for a swimming pool or a garden shed?

Yes. These works may be exempt from public consultation, but they still need approval from the municipal authority.

How long does the public consultation last?

30 days, starting the day after publication in the Feuille des avis officiels.

Where can I see projects under public consultation?

In the Feuille des avis officiels, on vd.ch, on the municipal noticeboard and at the municipal registry.

General information, updated October 2026. Every project is different: the rules for a given plot have to be checked case by case.

Let’s talk about your project.

A first meeting to understand what you want to do, where, and on what budget.

Type of work